14 June 2023 Media Release: GRDM Regional Waste Management Facility construction to start before July 2023

Media Release GRDM Regional Waste Management Facility construction to start before July 2023

For Immediate Release
14 June 2023

Garden Route District Municipality (GRDM) yesterday, 13 June 2023, held its official site handover meeting with Tefla Group (Pty) Ltd for the regional waste management facility. Before the commencement of this site establishment and construction of the facility, it was required to obtain the Construction Work Permit from the Department of Employment and Labour.

The Department of Employment and Labour fast-tracked the application process, which typically takes 30 days, after they received the application on 26 May 2023 and provided the approval on 8 June 2023.

Currently, Bitou-, Knysna-, George-, and Mossel Bay municipalities use the PetroSA landfill in Mossel Bay. PetroSA previously granted an extension of the current waste disposal contracts with the different municipalities for an additional twelve (12) months, which will end on 29 February 2024, when the site is expected to reach full capacity. By this time, an operational waste cell must be available at the newly constructed Regional Waste Management Facility for domestic waste disposal.

During the engagement, GRDM Municipal Manager, Monde Stratu, said: “Today is a huge milestone achieved for GRDM, and we look forward to seeing Tefla Group carry this forward.  Finally handing over the site, is something I never thought would happen in my time at GRDM. However, when I leave, I will be able to say that there is a large facility on the N2 that services four local municipalities.” Stratu thanked the Community Services Department and other role players who steered the project to this point, and he wished the contractors and project managers’ good luck in bringing the project to completion on time.

The Regional Waste Management Facility Management Project is a crucial initiative aimed at improving waste management practices within the region. Site establishment will now proceed for the next three weeks, which will be followed by the commencement of construction.

The estimated project timeline, taking into account local weather patterns, as well as the need to import most materials from Germany, is as follows:

Description Due Date
Contractor on Site June 2023
Completion of Phase 1 February 2024
Estimated completion of project March 2025
Operations & Maintenance Tender Award August 2023

-End-