Skip to content Skip to left sidebar Skip to footer

14 February 2024 Update 3 on the Construction of the GRDM Regional Waste Management Facility

Update 3 on the Construction of the GRDM Regional Waste Management Facility

14 February 2024

Bulk earthworks, including the final shaping of Cell 1A and excavation of the leachate and contaminated water dams, are in progress. The road box cut has been completed for the entire access road of 3.8km and the contractor has commenced with the road layer works.

The excavation of the subsoil drainage trenches in Cell 1A is in progress and all the required materials for the installation of the subsoil drainage is on site. The completion of the subsoil drainage will be followed by the installation of the various liners as legislatively required to prevent any underground water or environmental pollution. The clear & grub and removal of topsoil on Cell 1B (adjacent to Cell 1A) is also in progress.

There have been several delays in the construction process to date, however, all avenues to expedite the project is currently being pursued and a revised programme is to be submitted to Garden Route District Municipality (GRDM) by 16 February 2024.

-END-

There are currently various activities taking place at the Regional Waste Management Facility in Mossel Bay.