20 February 2024 Update: Gwaiing Road Construction Works, George

Update: Gwaiing Road Construction Project

20 February 2024

The Gwaing project is still in its construction phase with 65% works completed.

The main focus areas currently are the processing of the layer works, where the team will soon commence with the stabilisation process of the first lane, as material is currently being carted into the site from the approved source. Various other activities are still in process such as the improvement of the drainage network by means of laying new stormwater pipe crossings, which are nearing its completion.

The final completion date set for 18 September 2024.